Next: Kinematic distributions
Up: First look at the
Previous: Introduction
The runs 20056,20059,20077,20118 were analyzed to check the efficiency of level 2
hardware. The run 20056 was in the real rejection mode and the run 20118 was with
trigger bit 1 off. The tracks identified by the level 2 hardware, were extracted
from the TGBI bos bank (Level-2 sector information), and compared with the tracks defined after
RECSIS hit base reconstruction from HBTR bos bank on event by event basis.
From each run 70000 triggers were included in the analysis.
The table 1 summarize event numbers in those runs.
Table 1:
Level 2 and hit base events. Column 2- are all events with class type=3 (charged trigger),Column-3 and 4
are subsamples of Column 2 with event type=1 (LVLT2 accepted) and type=4 (LVLT2 rejected), Column-5 and 6 are
tracks from HBTR without and with cut on class type=3, Column-7 all tracks with LVLT2 OK (including bit 1)
Run |
evtclass=3 |
3/1 |
3/4 |
HBTR events |
HBTR/3 |
LVL2 OK |
20056 |
47700 |
47700 |
|
34251 |
31946 |
70000 |
20059 |
48561 |
31279 |
17282 |
26528 |
20737 |
48115 |
20077 |
51538 |
32335 |
19203 |
24831 |
19426 |
46594 |
20118 |
70000 |
46923 |
23077 |
31530 |
31530 |
46869 |
The comparison of Run 20056 and 20059, which were done under the same trigger conditions (bit 1 and 3 on),
shows, that the number of hit base tracks for the same number of total events (70000) is increasing
about 1.5 times (the ratio of corresponding numbers in column-6).
Roughly 50% (excluding sector 4) of tracks passing through the Level 2,
are giving an input in the hit
base track bank (see Figs. 1,2). The difference in the number of
tracks in events with identified tracks is shown in Fig. 3.
The number of hit base tracks in different sectors for this two runs is similar and the
ratio of hit based tracks to LVL2T tracks is exactly the same (see Fig.2).
This probably means that the software and
hardware rejection are performing in the same way.
Comparison of hits from reconstructed
tracks (RECSIS) with tracks identified by Level 2 hardware for different sectors is presented in
Fig. 4. The main message of that plot, is, that almost
100% of reconstructed (RECSIS-HBTR) tracks have a correct sector
identification on Level 2 hardware level. Very few tracks have 1 sector shifted between software and hardware.
The tracks from HBTR bank rejected by the Level 2 versus the sector number are shown in Fig. 5.
Majority of that rejected tracks have a sector properly identified by Level 2 hardware, and was rejected for some unknown reason. The number of
rejected (miss-rejected) tracks is much lower when the neutral trigger (bit 1 ) is off,
even if the tracks included in the
consideration were all choosen to have event class(in HEAD bank) equal 3, which corresponds to the
charged trigger.
The kinematic distributions of rejected by Level 2 hit base tracks (less than 1% in worse case), are shown in
the Fig. 6.
Figure 1:
The number of LVL2 tracks (upper solid line in all plots) and corresponding
number of hit based tracks from HBTR. The lower lines are solid Run 20059,dashed Run 20077 ,dotted Run 20118 and
dash-dotted Run 20056.
|
Figure 2:
The ratio of hit based tracks from HBTR to the number of LVL2 tracks. (see. 1)
|
Figure 3:
Difference in total number of tracks per event between
Level 2 and hit base tracking.The bottom plot was done, without the sector 4 tracks. Sector
4 was malfunctioning during that runs.
|
Figure 4:
LVL2 sector reconstruction efficiency. Shows the difference
in the sector number, for tracks from HBTR (hit base tracking) and
TGBI (Level 2 hardware). Zero means the sector is the same, and minus 1 means
the sector is different (typically the neighboring one).
|
Figure 5:
LVL2 sector inefficiency: Tracks in HBTR rejected by the
Level 2 hardware. Rejected tracks mainly have hits in Level 2 appropriate sector
information, but were marked as bad for some reason.
|
Figure 6:
Kinematic distributions of tracks from HBTR rejected by LVL2.
|
Next: Kinematic distributions
Up: First look at the
Previous: Introduction
Harout Avakian
8/31/1999