|
|
FEL Commissioning Activities
We discussed the hardware and software tasks to achieve 1 kW Lasing. Although there has been
significant progress on the list most tasks remain only partially complete. Efforts need to focus on
the must-have actions for the 1 kW lasing.
Hardware progress toward getting the beam recirculated is farther along. Significant installation
activity during the last week has moved us closer to completion of the systems. Most systems are
in place and believed to be operational. That is, we will find out next week during beam operations
what remains on the punch list. All system owners are to perform a hot check of their system
before signing it off by next Thursday.
A 5F region BPM is unavailable due to our failure to fix the vacuum leaks on the feedthroughs. A
second try is underway but if that fails we will remove a BPM in the 4F region (IPM4F09) on
Monday and install it in the 5F region so we have at least minimal diagnostics there. MPS
checkout will proceed next Tuesday so that we have permissives for recirculation when we come
up on Thursday. Initial plans will be to lase at 5 microns using the high power 10% outcoupler
mirrors.
A schedule has been produced for the next two weeks which has us doing that lasing, doing initial
recirculation, and providing light for the first user demonstration in Lab1.
We went over in detail the remaining "Subsidiary Tasks for Phase-Space Metaprocedure", and the
revised list is published in the Commissioning meeting minutes from July 17.
J. Boyce presented the eight remaining open actions from the ARR which must be accomplished
before routine operation of the user facility can proceed. All actions got assigned and only one
appeared to have significant impact: closing the shutter to the user lab when the machine is off for
extended periods. K. Jordan is looking at the PLC implications of that requirement and the best
method to incorporate the change.
|
|