Fire Protection Manual

Chapter 10

Fire Barriers

 

1.0           Purpose

Most building construction includes the use of fire barriers to protect the occupants in the event of a fire emergency. Fire barriers embody many features that must be kept intact for the barrier to perform its intended protective function. Inspection of fire barriers must be conducted throughout TJNAFs buildings.

2.0           Scope

This document provides the requirements for inspection of fire barriers.

3.0           Responsibilities

Note:    Management authority may be delegated to a task-qualified TJNAF employee at the discretion of the responsible manager.

·       Building Managers and Safety Wardens

-      conduct regularly scheduled walk throughs of all spaces

-      document walk throughs and findings

·       Fire Marshal

-      conduct fire barrier inspections

-      maintain inspection and evaluation records

4.0           General Information

4.1           Fire Barriers and Fire Walls

·       Fire Barrier Wall or Fire Partition Wall – an interior wall that serves to restrict the spread of fire, but does not qualify as a fire wall.  A fire barrier wall subdivides a floor or an area and is erected to extend from the floor to the underside of the floor or roof above. Fire partitions may be constructed of noncombustible, limited combustible, or protected combustible materials; and, should be attached to, and supported by, structural members having fire resistance at least equal to that of the partition.

·       Fire Wall – a wall of sufficient fire resistance, durability, and stability to withstand the effects of an uncontrolled fire exposure, which may result in collapse of the structural framework on either side. Openings in the wall, if allowed, must be protected. Fire walls, constructed of reinforced concrete, concrete blocks, and sometimes brick, provide a fire separation between areas of the same building.  A fire wall can separate buildings or subdivide a building to prevent the spread of fire.

·       Fire Walls, Fire Barrier Walls, and Fire Partition Walls

o   Designed and installed during new construction, these walls should be inspected and accepted at the time of construction.  Refer to National Fire Protection (NFPA) Code 5000 (6.1 below) for a comprehensive list of present-day design criteria used during new construction. The pertinent sections of this code are:

§  8.3.3, Fire Walls

§  8.4, Fire Barrier Walls

§  8.6, Horizontal Assemblies

§  8.7, Opening Protectives

§  8.8, Penetrations

o   Inspected annually

4.2           Fire Door Assemblies

To satisfy the requirements of NFPA Standard 80, Section 5.2.1 (6.3 below), fire door assemblies are inspected and tested not less than annually; and, a written record of the inspection is signed.

4.3           Fire Dampers

To satisfy the requirements of NFPA Standard 80, Section 19.4.1 (6.3 below), fire dampers are tested and inspected one year after installation. The test and inspection frequency, is, therefore, every four years.

5.0           Process

Fire Wall, Barrier Wall, and Partition Wall Annual Inspection

5.1           Inspect the walls that comprise a fire barrier in each location listed in Section 7.0, Fire Barrier Locations. All portions of the wall are to be viewed. Fire barrier walls are continuous through all concealed spaces, e.g., those found above a ceiling, including interstitial spaces. Inspect each wall using the following criteria:

·       Opening protectives: fire doors installed in a fire barrier wall are self- or automatic-closing. In accordance with the requirements of NFPA 80 Section 5.2.3 (6.3 below), Functional Test, all openings are protected by approved, listed, and labeled fire door and fire window assemblies, & their accompanying hardware (including all frames, closing devices, anchorage, and sills).

·       Penetrations for cables, cable trays, conduits, pipes, tubes, combustion and exhaust vents, wires, and similar items to accommodate electrical, mechanical, plumbing, and communications systems that pass through a wall, floor, or floor-ceiling assembly constructed as a fire barrier are protected by a firestop system or device.

·       Ducts and Air Transfer Openings: fire dampers are installed to protect ducts and air-transfer openings that penetrate fire barriers and fire walls, as required by other sections of NFPA 5000 (6.1 below). It is important to note that not all ducts are required to be installed with dampers (see NFPA 5000 [6.1], Section 8.8.8.2 Fire Damper Requirements).

5.2           Complete an inspection record and sign the final Inspection Report.  The report shall include the following information:

·       Date of inspection

·       Name of facility

·       Address of Facility

·       Name of person performing the testing

·       Company name and address of inspecting company

·       Signature of inspector of record

·       Opening identifier and location of each inspected and tested fire door assembly

·       Type and description of each inspected and tested fire door assembly

·       Verification of visual inspection and functional operation

·       List of deficiencies

6.0           References

Note:    Unless otherwise noted, the following documents are the current editions.

6.1           NFPA 5000, Building Construction and Safety Code

6.2           NFPA 221, Standard for High Challenge Fire walls, Fire Walls, and Fire Barrier Walls

6.3           NFPA 80, Standard for Fire Doors and Other Opening Protectives

 

 


7.0           Fire Barrier Locations

Appendix

Building

Fire Barrier

1

#8 CHL

Exit Stair Enclosure

2

#12 CEBAF Center

Stairwell A, B, C, D, E, F, G, H, I,

F-Wing\Attrium\Kitchen common wall

Atrium walls

Elevator Enclosure – Wing AB

Elevator Enclosure – Wing F

3

#18 LERF

Skylight Stairwell

Elevator Enclosure

4

#28 SSC

Boiler Room

5

#67 South Access Building

Tunnel Exit Stairwell

6

#58 Test Lab

High Bay\Annex Wall

Annex East Stairwell

Annex West Stairwell

Electrical Rm 1101/Corridor 1000A

Electrical Rm 1101/Mechanical Rm 1102

Process Support Area Rm 1050 & Corridor 1004 (2 hour rated)

Process Support Bldg Rm1001A/Corridor 1002

Stairwell North - Area G

Elevator Enclosure – Area G

Stairwell West – Area G

7

#38 North Access Building

Tunnel Exit Stairwell

8

#97 Counting House

Stairwell

Hall A Cable Shaft

Hall B Cable Shaft

Hall C Cable Shaft

Elevator Enclosure

9

#98 CRYO Fab. Shop

Common Wall with electronics area

10

#202 Hall D Counting House

Dumb Water Enclosure

Exit Stair Enclosure

Common wall with Hall D

n/a

#55 Technical Engineering & Development (TED)

Electrical Rm 1515

Entry Foyer

West Stair

Elevator Enclosure

Electrical Rm 2526

n/a

#94 Hall B

Labrynth Exit

n/a

#96 Hall C

Labrynth Exit

n/a

#101 Hall A

Labrynth Exit


8.0           Revision History

rev

summary

date

3.0

triennial review

-  added Note to 3.0, Responsibilities

-  updated

-  header and footer per discussion with T. Minga, 04.15.2022;

-  8.0 per footer dates, as well as format of 8.0;

-  made general edits and format updates (e.g., bullets, spacing, etc.)

-  relocated sections 6.0 & 7.0 to be in line with 1.0 to 5.0; and more easily accessible

-  added a Note to 6.0 regarding current editions

-  new 7.0 is the Fire Barrier Locations table

-  made the Building Floor Plans into appendices 1 through 10

05.12.2022

2.1

updated TPOC (chapter author) and Fire Protection Manager from E. Douberly to T. Minga

06.02.2019

periodic review - no changes per TPOC (author)

06.02.2016

qualifying periodic review; clarified Inspection Report requirements; updated Fire Barrier Locations

09.17.2013

2.0

separated “Combustible Loading” content to Chapter 11

02.10.2011

1.0

updated to reflect current laboratory operations

10.01.2009

 

 

 

 

 

 

ISSUING AUTHORITY

AUTHOR

APPROVAL DATE

NEXT REVIEW DATE

rev

 

 

Fire Protection Department

Tim Minga

05.12.2022

05.12.2025

3.0

 

This document is controlled as an online file.  It may be printed but the print copy is not a controlled document.

It is the user’s responsibility to ensure that the document is the same revision as the current online file.  This copy was printed on 5/11/2022.