Fire Protection Manual

Chapter 4, testing procedures

 

 

 

 

 

Appendix 11: Examining the Full-Flow Trip Test of the

Preaction Water Sprinkler System

 

 

 

 

1.0           Purpose

Improper priming water levels can adversely affect the operation of supervisory air within preaction water sprinkler systems. This document provides a procedure to conduct a full-flow trip test of a pre-action water sprinkler system, which is required by NFPA 25, Standard for the Inspection, Testing, and Maintenance of Water Based Fire Protection Systems, Chapter 13, Section 13.4.3.2.

2.0           Scope

This test shall be performed on each preaction water sprinkler system within three years of the last test during a scheduled shutdown.

3.0           Planning

Notify the facility work coordinator using the approved electronic work control notification procedure. Allow one week for approval of the requested work; be prepared to reschedule the requested work to satisfy the area’s production schedule. 

Testing requirements include:

·       3 staff members

·       4 hours of time

·       equipment

o   Manufacturer’s Manual (see Section 8.0)

o   Full-Flow Trip Test Data Sheet

4.0           Test Preparation

4.1           Ensure access to the necessary equipment is available and does not interfere with accelerator operation.

4.2           Use Chapter 5:  Fire Protection System Impairment Procedure for detailed instructions on work planning, advanced notification, and administrative controls.

4.3           Post the Fire Alarm Systems Testing in Progress sign(s).

4.4           Notify the technical representative (TR) to witness the test.

4.5           Evacuate the hazard area of all personnel.

4.6           Disconnect the building audible alarms at the Fire Alarm Control Panel (FACP).

4.6.1      Station a knowledgeable technician at the FACP at all times that the audible alarms are disconnected.

4.6.2      This technician is to remain attentive at the FACP at all times that the audible alarms are reconnected.

4.6.3      In the unlikely event an unanticipated fire alarm signal is received on the FACP, the technician shall reconnect the building audible devices and join the building evacuation.

4.7           Disconnect the preaction water sprinkler system and tag out.

5.0           Test the Priming Water Level

5.1           Open the priming level test valve.

5.2           If water flows, drain it.

5.3           Observe the water discharge patterns from all open spray nozzles or sprinklers to ensure the following:

·       patterns are not impeded by plugged nozzles,

·       nozzles are correctly positioned, and

·       obstructions do not prevent discharge patterns from wetting surfaces to be protected.

5.4           Close the valve when water stops flowing and air discharges.

5.5           If air discharges when the valve is opened, the priming water level could be too low.  To add priming water, refer to the manufacturer’s instructions.

5.6           If obstructions are found, perform the following steps until all obstructions are clear and the discharge pattern is unimpeded:

5.6.1      Clean the piping and sprinklers or nozzles.

5.6.2      Retest the system.

6.0           System Restoration

6.1           Reconnect the preaction water sprinkler system; remove the lock out tag out.

6.2           Reconnect the building audible alarms at the suppression control panel.

6.3           Dismiss assisting technician at the FACP.

6.4           Remove the Fire Alarm Systems Testing in Progress notification signs previously posted.

6.4.1      Notify the TR when the tests are complete and the system is on-line and operational.  Allow the TR to verify normal operating conditions of the system.

6.4.2      Allow personnel to return to the area previously designated as hazardous.

7.0           Conclusion

Upon completion of the procedure, the preaction water sprinkler system is on-line and operational.

8.0           References

·       Manufacturer’s Manual

·       NFPA 25, Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection

9.0           Revision History

rev

summary

date

1.0

triennial review

-  updated

-  header and footer per discussion with T. Minga, 05.05.2022;

-  9.0 per footer dates, as well as format of 9.0;

-  made general edits and format updates (e.g., bullets, spacing, etc.)

-  corrected acronyms and abbreviations (e.g., SOTR to TR)

-  replaced previous red-boxed links with more up-to-date red-outlined box links (see below)

05.19.2022

0.1

periodic review; no changes per TPOC

06.02.2019

periodic review; no changes per TPOC

06.02.2016

minor reference clarification

04.23.2015

0.0

initial release

06.16.2011

 

 

 

 

 

ISSUING AUTHORITY

AUTHOR

APPROVAL DATE

NEXT REVIEW DATE

rev

 

 

Fire Protection Department

Tim Minga

05.19.2022

05.19.2025

1.0

 

This document is controlled as an online file.  It may be printed but the print copy is not a controlled document.

It is the user’s responsibility to ensure that the document is the same revision as the current online file.  This copy was printed on 5/20/2022.