|
|
Commissioning Activities
There was no beam operations this week. Last weekend, expecting to be checking out diagnostics
(specifically the Happek devices) in some depth through the week, we heat treated the cathode so
we could start fresh. On Monday afternoon, after cesiation, we attempted to ramp the gun voltage
to 350 kV without using the conditioning resistor. Unfortunately the gun began arcing at 300 kV.
We therefore inserted the conditioning resistor and did high-voltage processing overnight and part
of Tuesday, eventually reaching 420 kV. After recesiation, the photoresponse of the cathode was
very poor. Consequently we did another heat-treatment cycle and recesiation, but could not get
past 318 kV without arcing. There was evidence of field emission from the cathode itself, and so
we were concerned that arcing had splattered impurities over the gun's interior as had happened
early February. Therefore we decided to polish the surfaces electrically, i.e., do more high-voltage
processing. It turned out to be very easy to go back to 420 kV, where the gun sat quiet, and from
that we concluded the cathode is bad but the gun's surfaces are not likely to be contaminated with
splattered material. Consequently we decided once again (last night) to recesiate in hopes the
cathode would recover. It did not, but exhibited field emission at 350 kV. Thus, today we opened
the gun to proceed with changing out the wafer. We also developed a detailed timeline for
refurbishment, and the entire process will take two weeks. If all goes well, beam operations will
resume 1 Jun 98.
This week's developments were certainly unplanned and constitute a minor setback; however, the
downtime will enable us to turn attention to other productive activities that had been languishing.
For one, we will be able to complete a great deal of remaining short list of installation tasks,
including in particular the second 180-degree dipole magnet. Two weeks from now the
recirculation arc will be substantially complete. Still missing will be the sextupole magnets, due in
late July, some air-core correctors, and the beam scrapers.
Happek (Univ. of Georgia), it turns out, could not visit this week after all because he was unable to
complete fully his instrumentation. Thus the downtime enables him to finish carefully his two
interferometric bunch-length monitors and to install and carefully check them out without beam.
G. Krafft continues to work with Happek to coordinate completion of the diagnostic and arrange
his visit. At this writing (1555, 15 May 98), he is planning to arrive here Monday, 18 May 98.
The time also gives us a much-needed opportunity to digest what we have learned thus far about
the machine, and to write detailed procedures for establishing "lasing-quality" electron beam.
|
|