Jefferson Lab Weekly Briefs September 24, 2008

Jefferson Lab Weekly Briefs

September 24, 2008

12 GeV Upgrade

The CLAS12 drift chambers in Hall B are designed to provide high tracking accuracy, while maintaining high-rate capability and large acceptance. This necessitates small drift cells and very thin endplates with low-profile onboard electronics and cables. A full-scale prototype of a region-1 chamber was built, strung and instrumented as a joint JLab & Old Dominion University project. As a result, the construction technique was validated, and the board and cable mounting schemes were refined. Electrostatic deflections of wire positions were insignificant.

The Forward Drift Chambers (FDCs) in Hall D provide the necessary tracking of charged particles traveling in the forward direction through the GlueX apparatus. The test wire winding on four FDC composite wire frames has been completed at the Indiana University Cyclotron Facility. The test results indicate that the composite wire frame design meets all structural requirements and validates that the required precise tolerances for relative position distribution and wire tension can be met. Valuable lessons were learned to improve on FDC construction.

Physics

In Hall A, installation of the polarized helium-3 target is proceeding smoothly. The assembly of the polarized target proper has been started with the oven now in position. The installation of the new electron detector for the Compton polarimeter, designed by the University of Clermont-Ferrand, has been completed, and the beamline is back under vacuum. The BigBite detector system has been installed in place and surveyed. The cooldown of both High Resolution Spectrometers (HRS) is underway, with the left one on cold return and the right one to follow as soon as the cooldown of the left has been completed.

In Hall B, the cooldown of the Torus magnet began on Sept. 18 and is expected to continue for 10-12 days. After that, the Saclay Solenoid magnet will be cooled down. The Cerenkov counter has been closed up again and leak tested, waiting for a final testing of the new lifting fixture for installation in CLAS. The inner calorimeter needed for the E1-DVCS run has been moved to the Hall for final preparations.

In preparation for the Spin Asymmetries of the Nucleon Experiment (SANE) in Hall C, the polarized target girder and the polarized target service platform have been installed. A detector shielding wall has been installed near the target. The polarized target has been moved into the hall and is being readied for installation.

Accelerator

The unit substation LN1 rebuilt transformer was delivered and then installed with the help of a crane. After the electrical connections were made, LN1 was powered successfully. The warmup of Cryomodule SL05 was begun. Turbines on the Central Helium Liquefier Main Cold Box were re-started after the replacement of compressor C-6’s main shaft seal. Personnel Safety System certification of RF (radiofrequncy) and box supplies continued.

Free-Electron Laser (FEL)

The FEL is being prepared for startup of operations. The advanced drive laser is ready, the SRF (superconducting radiofrequency) cooldown started, and the gun high-voltage processing is underway.

Theory Center

A recent Theory Center paper (arXiv:0809.2582 [hep-ph]), featuring a collaborative effort with an Old Dominion University undergraduate supported by the JSA RIFA (Research Internship for Foreign Undergraduates) program, considers how the results of lattice QCD calculations of charmonium can be reconciled with successful non-relativistic potential models. It provides a bound-state model description of lattice data that indicates, for example, "hybrid" states, which require excited gluonic fields in their structure - a suggestion that is becoming increasingly relevant experimentally with observations of states like the Y(4260). The light-quark analogs of these states form the principal focus of the GlueX experiment.

Engineering

The Safety Systems group completed the functional certification of the CEBAF accelerator, an important step required for upcoming operations. Functional certification involves verifying that the PSS can shut off hazardous equipment if needed.

The alignment and metrology group completed the transfer of the CEBAF accelerator coordinate control to the new surface monuments. The coordinate system in the main accelerator is required for the construction of Hall D. Preliminary reduction of the data, at 1 sigma, show errors of less than 0.5 millimeters over the length of the accelerator linacs, or an error of 1.2 parts per million.

JLab's Safety Numbers

14 Days since Last Recordable Accident (JLab record: 331)
14 Days since Last Lost Workday Accident (JLab record: 676)

JLab Calendar of Events

Sept. 25: JSA's Electronic Commerce Vendor Show
Oct. 1-4: Workshop on Sources of Polarized Electrons and High Brightness Electron Beams (PESP2008)
Oct. 7: American Red Cross Blood Drive
Oct. 13-15: Electromagnetic N-N* Transition Form Factors Workshop
Oct. 14: Science Series Lecture: Fun with Astronomy
Nov. 27-28: Thanksgiving holidays - JLab closed

 

 

 

Environment, Safety, Health & Quality

The Quality Assurance and Continuous Improvement organization is in the process of transmitting a series of procedures to a variety of site personnel for required reading and/or general QA/CI program awareness. The organization is working with Division Safety Officers to determine a list of who should read and understand such procedures. In addition, QA/CI organization personnel are beginning a series of quality and safety minute presentations for MCC, FEL, SRF, and other weekly meetings to educate and/or demonstrate the procedures, processes, systems and tools expected to be a part of the site-wide QA/CI programs. If you have any questions about the JSA QA/CI program, feel free to contact Bruce Lenzer, QA/CI Manager, x7586.

Records Management for Individuals
Any document that you create that could be considered evidence of our organization, functions, policies, decisions, procedures or operations is considered a "record." There are certain instances in which the records must be managed, which includes retention and disposal requirements. A new QA procedure describes how individuals at JLab manage the records they create or receive during their JLab activities. If you create a JLab record, you can read the procedure at Records Management for Individuals - Procedure for information or speak to your Divisional Record Coordinator.

Beware of Poisonous Spiders Onsite
JLab is in a natural setting, and as such, we interact with all types of wildlife. Most of this wildlife will typically not enter buildings. However, sometimes spiders will seek dry, dark areas; therefore, we need to be aware of the hazards and implement the proper controls. Further details can be found linked off of Insight.

Computing and Networking Infrastructure (CNI)

CEBAF Center Wings A&B Network Outage
The network in CEBAF Center wings A&B will be unavaliable for several hours on Monday evening, Sept. 29 starting at 5 p.m. The network switches are being upgraded to support automatic VLan assignment. Please visit http://reggie.jlab.org to ensure that your machine(s) are registered. If you are still offline on Tuesday, Sept. 30, contact the HelpDesk at x7155.

JLab Computer Purchasing Policy
JLab is committed to reducing its energy consumption and purchasing more environmentally friendly products. To help achieve these goals, all new computer purchases must meet the minimum requirements of the Silver tier rating of the Electronic Product Environmental Assessment Tool. During the coming month, JLab's CNI group will publish a standardized list of computing systems for lab personnel that meet the requirements defined by EPEAT for Silver tier systems. This list will provide a variety of system specifications that have been loosely configured to meet the various categories of work (CAD/Engineering, Physics, Administration, Software Development, etc.) performed at JLab. In addition to meeting the emerging requirements for energy efficiency, reusability and recyclability as defined in new and existing DOE requirements, the list also will ensure that systems purchased for JLab work are appropriate for the work performed.

A purchasing policy will be released October 1 that further explains how this program will be implemented in the future. Additional information on EPEAT can be found at: http://www.epeat.net/.

For now, those wanting to procure a new desktop system can submit a CCPR stating who the system is for, how it will be used and what Project and Org to use for the purchase. The CNI group will submit a requisition for the appropriate system on their behalf.

P2P Software Not Allowed on JLab Network
The CNI group reminds computer users that JLab's cybersecurity policy prohibits the use of Peer-to-Peer (P2P) software on Lab systems or networks. Common examples of prohibited P2P software include BitTorrent, LimeWire, Gnutella, TVAnts, eDonkey, Azureus/Vuze, FlashGet, uTorrent, and many others. The only P2P application currently allowed on JLab networks is Skype, as long as JLab's Skype configuration guidelines are followed (see below).

Effective immediately, systems participating in prohibited P2P traffic will be automatically blocked from the JLab network for one hour. At the end of the hour, the ban will automatically be lifted and normal network access will resume if the P2P activity has stopped. This is a change from the current procedure, which requires the user to contact the HelpDesk and have the ban lifted manually. This change should help users who get blocked during weekends, holidays and other times when the HelpDesk is closed.

For more information about JLab's P2P policies, visit the following links:
DOE TMR-18 Peer-to-Peer (P2P) Networking
Jefferson Lab Skype Usage Policy
Tips on Skype Configuration

Announcements

JSA Electronic Commerce Vendor Show
The entire JLab community is invited to the annual JSA Electronic Commerce Vendor Show tomorrow (Thursday, Sept. 25) from 9 a.m.–2 p.m. in the CEBAF Center atrium and room F113. Come meet the many vendors and manufacturers that will be showing off their products and answering your questions. Enjoy give-aways, free samples and refreshments. For additional information, contact Renee Carter at x7954 or carter@jlab.org.

Blood Drive Set for October 7
The next American Red Cross Blood Drive is scheduled for Tuesday, Oct. 7, from 10 a.m. to 4 p.m. in CEBAF Center F113. New and repeat donors are encouraged to attend. Appointments and walk-ins are welcome. Contact Johnie Banks at x7539 or jbanks@jlab.org to schedule an appointment or to volunteer.

$4-off Coupons for State Fair Ride Wristband
The State Fair of Virginia runs Sept. 25 - Oct. 5. A supply of State Fair brochures and $4-off ride wristband coupons are currently available at the CEBAF Center, VARC and ARC reception desks. This is the last year that the State Fair will be held in Richmond at the Richmond International Raceway. Next year, it will be held at its new home in Caroline County north of Richmond on I-95.

Tee'em Up for the JLab 2008 Fall Golf Tournament!
The tournament will be held on Wednesday, Oct. 8, at the Williamsburg Country Club in Williamsburg. The event will begin at 1 p.m. with a shotgun start. The tournament will be a four-person Captain's Choice. All teams will be handicapped. There must be at least two JLab employees per team. The cost for JLab employees is $45 each, and the cost for non-JLab employees is $60. The fee includes range balls, green fees, cart, food (afterwards) and the prize fund.
 
See Danny Machie (ARC 402/09, x7501) to sign up. Golfers must list their average score for 18 holes, and checks should be made payable to Danny Machie. The entry deadline is Friday, Oct. 3.

 

 

Privacy and Security Notice