18 September 1990 - Blue Sheet

PDF Download

Project Progress Summary

18 September 1990

Injector and Front-End Test

-Injector main pump and vacuum manifold installed.

-Fabrication of 5-MeV chicane vacuum chambers started on schedule at University of Illinois.

-Cables for injector magnets and controls pulled.

-First cryomodule has been mounted on its stands and cabling is proceeding.

-Vacuum pumps and manifold have been installed on the injector girder as injector reassembly continues.

-Electronics in the high-voltage cage for the fun were run successfully from the control room.

-Welding and leak checking of Helium transfer line end box for FET is under way.

-Dummy load for testing magnet power supplies is in tunnel. Power supply rack is undergoing installation in injector service building.

WBS 1

-The High Bay cranes have been downrated to 2-ton capacity until repairs on the cables are completed.

-John Brawley electron beam welded 2 windows; both leak checked tight. They need coating and RF testing. They should be delivered to the cavity assembly area tomorrow.

-The third cryounit is waiting for the SMA connector. Cryounit #4 is being welded into the helium vessel.

-Meyer Tool will reply to Mark Waite by fax on the status of end can delivery. The current schedule is 1 October for the first end can and 15 October for the second.

-Cryomodule #1 is being rough-aligned in the tunnel. The third warm pipe was baked last week, the fourth is being assembled this week, the dummy cryomodule pipe is to be assembled.

-The quarter-cryomodule has been tested.

-Cleaned and assembled ten HOM loads to see if they stay clean for one to two weeks. If so, pre-assembly can be done here before shipping them for brazing.

-Brazing run with six windows had 100% success rate. These are BT brazed and need to be temperature cycled.

-Tested Al2O3 powder ceramic; it was cracked during grinding. The Q measured 1x 10^5 sitting in the frame. This is .9999% pure alumina.

WBS 2

-The first two girders for the magnetic elements for the Front End Test were assembled, aligned, and delivered to the accelerator tunnel.

-The installation of the linac pedestals started.

-The drawing of a prototype solid yoke for a QA quadrupole was sent to Procurement for fabrication.

-Studies of impact and solutions for the offset beam switchyard tunnels (A & C) were started.

-Layout of the 45-MeV spectrometer for the end of the Front End Test, using existing stand hardware and elements, was started.

WBS 3

RF Power:

  • Applied power to the HPA and started checking interlocks and controls. ETM is shipping two more HPAs this week.
  • Received six more modified circulators from Ferrite Components. Tested one unit with good results. Will test the remaining five circulators this week.

RF Controls:

  • Received 25 RF panels from Advex.
  • Module front panels being silkscreened and fabricated.
  • Waiting on IF board from vendor.
  • Transformers being fabricated at Blue Crab Road.
  • Analog board in process of being stuffed.
  • All digital boards are in house.

WBS 4

-Finished WBS 7 cable pull.

-Installed trim system rack in injector service building and connected to 32-channel dummy load in tunnel.

-Completed general system drawing for the trim system rack.

-Finished FET cable pull schedule for WBS 2 VAC system and ordered cable and transformers for VAC ion pumps.

-Received seven transformers for arc service buildings.

WBS 5

Controls:

  • Running HPA test software on local computer in injector service building.
  • Ran first tests of gun controls from MCC.

Safety:

  • Completed access room wiring in injector and north access buildings.

Beam Diagnostics:

  • Completed detector board schematic and started art work for 1500-MHz monitor.

WBS 6

-Hall C dipole RFR went out 13 September.

WBS 7

-Dual 80-K purifier piped. LN2 dewar and connecting piping 85% complete.

-NW end box 2-K circuit installed along with NE quadrant supply transfer line 2-K circuit. Welding and leak-checking complete.

-Supply and return CHL transfer lines to south linac loaded into sleeves.

-Kinney pump in W5 building was checked out after power connection; breaking trips. Kinney notified and replacement shipped. Also pulley in blower shaft fractured; replacement shipped.

-Warm gas interconnection line fabricated by cryo group. Two 80’ sections given to WBS 8 for in-ground installation.

-30,000-gallon LHe dewar complete at CVI. Waiting for shipment permits; should ship this week.

-10,000-liter dewar cold-shocked and leak-checked. No apparent leaks.

-CVI/CEBAF completed pressure test on 4-K system with nitrogen. Repair in process. GHe pressure test was to start Monday, 17 September.

-Main cryoline from 30,000-liter dewar to bayonet can be fabricated; will be installed prior to dewar delivery.

-CTF is operational on the cryounit; vertical dewar this week also.

-Started loading purified recovery piping to south linac.

-Terminating cables to injector cabinets for FET.

-Completing power connection to the CHL recovery compressor.

-Developing software for the cryogenic controls for the FET.

-Installing water filters for the CHL Kinney vacuum pump.

WBS 8

Accelerator Enclosure:

  • Completed painting the east arc tunnel.
  • Completed the siding on the west arc service and exit stair buildings. Roofing and interior work continuing.
  • Continued with underground utilities to the south linac service building.
  • The contractor has permanent power to the south access building.
  • Virginia Power continues to work on the power line to the master substation. They plan to energize the substation no later than 15 October.

End Stations:

  • Subcontractor reported a nonconformance is the BSY tunnel location. CEBAF is evaluating correction options.
  • Forming the second lift on the counting house stairs and elevator shaft walls.
  • Continued to form and pour beam line tunnel walls to Halls A and C and the SOG to Hall B.
  • Completed excavation for beam dumps A and C.
  • Began placing lean concrete in beam dump C.

EEL Building:

  • Formal joint contractor/CEBAF punch list inspections will begin this week. The anticipated BOD is 1 October.

Linac Installation

No report received.

Accelerator Division Support Services

Machine Shop:

  • Faraday cup fabrication completed (WBS 5).
  • FET tunnel model now displays HPA and power supply cabinets.

Stockroom:

  • Two new electronic kits were added to support WBS 5.

External Fabrication:

  • 25-W cooling plate drawings complete and parts being processed (WBS 3).
  • Procurement package developed for 38 beam viewers (WBS 5).
  • Run safe box parts for FET received (WBS 5).
  • Power supply chassis and crates due this week (WBS 4).
  • Beam steering coil (50 ea) and yoke (12 ea) ordered.

Linac 90 Conference

CEBAF staff presented a dozen papers at Linac 90 in Albuquerque last week.