Project Progress Summary
5 September 1990
Injector and Front-End Test
-Waveguide connections to the first HPA have been done and klystrons are being installed.
-Plumbing for injector service building has been installed. LCW system operational.
-The approach has been defined for cryomodule installation sequence. First cryomodule slated to be installed by 7 September.
-Injector girder has been surveyed and bolted to floor.
-The grouting of the stands for the injector elements of the front-end test was completed.
-The grouting of the stands for the injector elements of the front-end test was completed.
-Conduit for the safety system has been finished. Many of the support elements are also installed: key box, status lights, card readers, door switches.
WBS 1
-John Brawley successfully welded an rf window frame. The weld parameters program works fine.
-The cryomodule is scheduled to be installed in the tunnel 6 September.
-The sixth cavity pair has been turned over to the cryounit assembly area. This will complete the cavities needed for the next full cryomodule.
-The acid transfer system for the on-line chem room is being commissioned.
-850 niobium disks for cavities have been inspected and meet specifications.
-The ¼ cryomodule is installed in the Test Cave; testing begins the week of 10 September.
WBS 2
-All magnets required for the FET were received.
-The preliminary requirements drawing and specification for the injector and linac tunnel water system was given to Plant Engineering for them to create a bid drawing.
-Installation of the injector service building water system neared completion.
-The survey group continued work on the skeleton traverse of the entire tunnel and fiducialized the quarter-cryomodule.
-The design for the FET spectrometer was approved.
-The spreader/recombiner dipole procurement package was issued to vendors.
-The conceptual method of accurately mounting the BPMs to the quads in the arcs using a captured pilot portion of the beam pipe was resolved and a verification program initiated.
WBS 3
RF Controls:
- Sent preliminary spec out for master oscillator.
- Prototype arc detector tested on cryomodule.
- Received first lot of 2.5-watt amplifiers.
RF Power:
- Now have 41 klystrons from Varian. Returned #30 – it appeared to have been dropped in shipment.
- The circulator problem was the circulator waster load matching. The had added a matching disk to the feed line; it will be redesigned for higher power rating.
- HPAs and power supplies installed in injector service building. First four klystrons and waveguide parts installed in the first HPA.
- LCW manifold for the injector 95% complete. Got water 4 September.
WBS 4
-Finished WBS 1 cable pull.
-Completed AC power wiring for first HPA unit.
-Ordered transformers and breaker panels for east arc service buildings through E-6.
-Received six more utility chassis for use in FET trim system for a total of seven on hand.
WBS 5
Diagnostics:
- Boards for 100 megahertz FET BPMs ordered.
- Line drive prototype design tested.
- Current to voltage converter design tested.
WBS 6
-Hall C support structure RFP expected to be issued 7 September.
-Hall C dipole RFP expected to be issued 11 September.
-Four bids received 12 July for CLAS torus (Hall B), preparing for BAFO request.
-Hall A dipole RFP used, and bidders conference held. Bids due 7 November.
-CLAS prototype chamber at BNL for testing.
WBS 7
-Preparing the 4-K system at the CHL for the pressure leak test.
-Final leak check of the 6-inch supply transfer line to the south linac completed.
-Completed leak check on the 10-inch line in the CHL return transfer line from the south linac.
-Completed the second bayonet can for the CHL LN2, distribution system. Vacuum jacketed pipe 90% complete; installation at CHL should start this week.
-Floor grating I-beams have been installed and painted at CHL. Installation of the grating should start this week.
WBS 8
Accelerator Enclosure:
- East arc service buildings have been punch-listed and contractor is cleaning up the list for turn-over on or about 1 October.
- LCW system (10”) has been brought online and is now providing LCW to the injector service building.
- Tunnel backfilling is completed.
- All structural concrete on this contract is now completed.
- Contractor has started paving along road by north linac service building and the east arc area.
- Virginia Power is completing clearing on south property line for running their overhead HV lines to the 40 MW transformer.
End Stations:
- Concrete walls under way on the counting house.
- Personnel access tunnels for all three halls are under way.
- Approximately 60% of the beam tunnels are poured.
- Dewatering piping is complete at halls A and C.
EEL:
- Topsoil is placed.
- Painting continues.
- Majority of pavement has been placed.
- Mechanical and electrical work continues.
Linac Installation
-Training on the installation Standard Operating Procedures was conducted with WBS 2.0 personnel.
-Continued to mount cable tray and safety system box way.
-Five sections of LHe supply transfer line were moved into the northeast linac tunnel. All sections are in place except the turnaround box.