9 October 1990 - Blue Sheet

PDF Download

Project Progress Summary

9 October 1990

Injector and Front End Test

-Local injector air line assembly started. Water has been run in girder.

-Klystrons were successfully tested at moderate power in the 8-seater HPAs.

-Cable pulling for safety system has been completed.

-Installation of all FET warm girders, except spectrometers, is complete.

-Beam-line vacuum hook-up to cryomodules is under way.

-Commissioning of the CHL continue; first stage compressors 1, 2, and 3 were operated.

WBS 1

-Assembled an in-house cavity pair last week; however, a flange leaked.

-The niobium purification furnace is being moved to the second floor of the test lab.

-Assembly of the second cryomodule should be completed by the end of October, with testing November. Three cryounits have the beam vacuum connected. One end can has arrived; the other was shipped 1 October. The waveguide bellows from Calorstat were shipped 13 October and should arrive 17 or 18 October.

-All WBS 1 vacuum components have ben baked and are ready for the FET. Pressure has not reached 10^-9 Torr yet.

-HOM loads: cleaned 116 flanges to prepare for brazing. Continue to thermal cycle completed loads.

-Work continues on the EBW fixture for the windows. Proceeding with the sputtering system modifications to increase the throughput. Two more sapphire windows made.

WBS 2

FET:

  • All construction project magnetic elements for the FET are now installed and aligned to be ready for vacuum tube, water and electrical hook-up. (Special FET elements, i.e., spectrometer and dumps, remain in procurement, fabrication, and assembly.)
  • The procurement and fabrication of the remaining diagnostic elements needed b the operations group for the FET was started.

Magnets:

  • The bids for the CEBAF-supplies QB quadrupole laminations were received.
  • The request for proposals for the QB quadrupole fabrication assembly was sent to vendors.

Magnets Stands and Installation:

  • Started organization of the assembly space for mounting and aligning of quadrupoles and corrector magnets on their girders for the remainder of the accelerator.
  • Girder stands for the arcs and adjustment cartridges for the arcs were sent out for bid.

Survey and Alignment:

  • The group finished the skeleton traverse of the entire enclosure.

WBS 3

Klystrons and Power:

  • Produced RF from first 8-seater. No major problems to date. First four klystron/waveguide assemblies complete.
  • Six klystrons arrived Friday. Fifty-two have now been received.
  • Additional flex waveguide was received from MEC.
  • Twelve additional circulators from FCI should arrive next week.
  • HOM filters should be at CEBAF by 15 October.
  • Directional couplers and transition tests were witnessed at the vendor’s location. Sixteen of each were promised 31 October.
  • Crowbar is functional, but fault current is excessive and causes circuit breaker trip. Still needs refinement. Remaining parts being ordered.
  • Capture section waveguide installed Friday, 5 October. Next week for quarter cryomodule.

RF Controls:

  • Twenty-three buffer boards and 20 CPU boards sent to vendor for stuffing.
  • In-house fabrication IF transformers 85% complete.
  • RF crate rear planes in-house.
  • Zone 1 RF control racks transported to injector service building (from Blue Crab).
  • One analog board has been built and tested.
  • Drawings of Star System are out for comment.

Other:

  • Except for capacitor (not yet here) injector HV power supply is assembled and hipotted. Capacitor is due 23 October.
  • Demand power system monitoring equipment print is complete.

WBS 4

-Completed emergency power as-built drawings for injector building.

-Finished installation of WBS 5 4” x 4” duct and conduit run for FET.

-Completed a cable pull for WBS 7.

WBS 5

RF Controls:

  • Continuing work on RF micro software.

Injector:

  • Continuing to update software for diagnostics.

Safety:

  • ODH cable runs complete.
  • Software loaded into PLCS

Diagnostics:

  • Continue stuffing 1500-MHz electronic modules.
  • Terminating diagnostic cables in tunnel.
  • Diagnostic racks wired

FET:

  • Cabling continues.
  • Software for injector test finished.
  • Most of the monitors installed.
  • All monitor electronics built.

North Linac:

  • Assembling of warm section continues.
  • Electronics production continues.

Arc:

  • Fifty arc monitors: orders placed; monitors will be electron-beam welded.

WBS 6

No report received.

WBS 7

CHL:

  • First-stage compressors have been started and checked out.
  • Stokes vacuum pumps for linac quadrant vacuum system operational.
  • Leak checking supply transfer line to south linac.
  • Recovery compressor and 80-K purifier ready to flow test.

Tunnel:

  • Ready to weld the 6-inch outer jacket in the NE quadrant of north linac.

Test Lab Fabrication:

  • 10,000-liter neck modification complete; ready to install.
  • Helium dewar line for CHL was 40% complete.

WBS 8

Accelerator Enclosure:

  • Continued painting the tunnel.
  • Continued roofing and interior work on west arc service and exit stair building.
  • Completed subgrade preparation for roads ‘and parking lots and will start placing the stone base this week. Expect to start paving next week.

End Stations:

  • Started saw-cuitting beam-tunnel A walls in preparation for necessary rework.
  • Completed the floor slab in Hall A.
  • Started forming and installing reinforcing steel in preparation for placing the concrete floor slab in beam dump A.

EEL Building:

  • Interior finish work is substantially complete.
  • Project punch list inspections are essentially complete.
  • The subcontractor is working on correcting punch list items.

Integration and Installation

-Injector song sheets for the tunnel configuration (dwg. 28401-E-000301), machine elements and girders (dwg. 28401-E-000302), and cooling water distribution have been signed off. Their release is held up pending the completion of a tunnel section view at STA 195. This section drawing will be finalized by 10 October.

-A group has been established to work with WBS 8 during the final inspection of electrical and mechanical systems being accepted from civil construction contractors. Members of the group are: Dana, Arenius, George Biallas, William Chronis, Nick Dobeck, Jock Fugitt, Tom Mann, Rick Nelson, and Claus Rode. A report will be issued on each subsystem when it is accepted.

 

Accelerator Division Support Services

Machine Shop:

  • Three beam dumps completed and delivered.
  • Five microwave-type beam position monitors completed and delivered (WBS 5).
  • Miscellaneous parts made for CTF upgrade completed and delivered (WBS 7).
  • Dial gauge support for dipole and girder alignment completed (WBS 2).

Stockroom:

  • Total business last week $45,160.47.
  • Three new kits: “Arc Detector,” “I/R Detector,” and “Interface” accepted and entered into inventory (WBS 3).
  • Delivered 23 CPU board lits and 5 BLM and PMT analog cards.
  • Seventy-nine fast shutdown kits delivered last week (WBS 5).

External Fabrication:

  • Fabrication jobs processed for FET: chicane magnet stand top plate, 45-Mev spectrometer WB magnet girder and girder modification, beam steering unit receptacle bracket, and differential pump station Z-axis adjuster.

Training Opportunities

-CPR, 17 October, 8:30-12:30, Rooms 53/55.

-Aerial Work Platform Operator, 24 October, 9:00-11:00, EEL.

-Additional training opportunities are listed in the Personnel Office’s yellow pamphlet for October and November.

Announcements

-Site-wide water shutdown scheduled for 9 p.m. on Saturday, 13 October.

-The Project Office will prepare a calendar-style project schedule again this year for general distribution at CEBAF. Suggestions, especially for technical illustrations to be included, are welcome. Please call Michele at extension 7564 with ideas.

-As of the end of FY 1990 the construction project is 51% complete.