Jefferson Lab Weekly Briefs June 13, 2012

Jefferson Lab Weekly Briefs
June 13, 2012

12 GeV Upgrade

The full research performance goal of the C100 cryomodules has been successfully demonstrated: 108 Megavolts while accelerating 465 µA (microamps) for more than one hour. The major installation work is well underway. The east recombiner has been removed and the removal of the west spreader has begun. Two new cryomodules (C100-4 and C100-5) have been installed. More than ten trim power supply racks have been installed. Installation of the compressors and 4.5 Kelvin coldbox for the Central Helium Liquefier-2 continues. The beam position monitors for arc 10 are ready for installation.

Physics

Staffers from all three halls have been consumed with various meetings, reviews and other items, including last week's JLab Users Group Annual Meeting and Workshop, followed by collaboration meetings for all three halls in June, plus other meetings.

Accelerator

This week was the final full week of running electron beam in the injector to support the Polarized Electrons for Polarized Positrons (PEPPo) experiment. The radiofrequency capture section, which had stability issues at the end of last week, remained stable, but Engineering Support personnel maintained a close eye on it. On Thursday afternoon, an anomaly with a cryogenic valve position indication caused a pressure surge that shut down the CHL, forcing PEPPo to pause for a few hours. Later that day, the South Linac tunnel was locked up in preparation for commissioning of the superconducting RF cryogenic module 2L23. The weekend was fairly quiet running. Early Sunday morning, the PEPPo beamline experienced a sudden change in vacuum. Investigation of the beamline and components revealed no reason for the change. A leak check found no leaks, and an analysis of the gasses inside the beamline showed the gasses weren't from the surrounding air, indicating the source of the drop in vacuum may have been from something outgassing within the beamline. The vacuum recovered and PEPPo was able to continue with little interruption until the accelerator was shut down and completely opened up for access for 12 GeV work on Monday morning.

Free-Electron Laser

The new Argonne-undulator-based ultraviolet FEL has been running well, and last week the FEL team optimized the lasing setup to produce 124 nanometer photons in the third harmonic. This photon beam was then brought up into User Lab 1, and its power and spectrum were characterized. On Friday, the user chamber for the Atomic Trap Trace Analysis work on krypton was connected to the vacuum system. In addition, the team continued re-work of the Darklight hardware to prepare it for fiducialization and installation in the coming weeks.

Engineering

With the start of the 12 GeV installation shutdown about two weeks ago, the Electrical Engineering Systems (EES) group has switched from largely accelerator operations support to multiple shutdown activities. Power supplies and RF systems have been shut down and put in a safe mode so that other tasks can begin. The magnet power supplies that are no longer needed have been removed to storage. The equipment tear out, for upgrades, of many accelerator components has required disconnecting thousands of power and signal cables prior to removal of the equipment. This work must be done carefully to prevent damage and to allow correct hook-up once the new hardware is re-installed. Nine EES personnel have been assigned to help other groups during the initial phase of the shutdown. Five people are working in Hall B on equipment and cable removal and another four are working with the Mechanical Installation group to assist in component removal. The safety systems group is engaged in revamping and modifying the Personnel Safety System to support the upgrades. Finally, a small cadre of people continue to support the remaining physics operation: the PEPPo experiment in the injector.

E-Sign System for Documents
The Document Control Group has worked with the IT Division's Management and Information Systems group to develop a paperless system of electronic signature and archival system, E-Sign, for engineering documents (i.e. drawings, specifications, calculations, etc.). E-Sign does not replace or compete with other lab document systems, such as Docu-Share or Library systems. This system will replace the current method (OCE) of retrieving archived documents, since OCE does not support new operating systems. This effort has many benefits to the lab with respect to cost and efficiency in processing engineering documents. Implementation is scheduled for July 1.

E-Sign has been tested throughout the lab in two phases to include novices as well as seasoned users of the current paper system. To ensure a smooth transition from the current system to E-Sign, several training sessions are being scheduled between June 15 and June 30. Training documentation is also available on the M:drive : M:dcgE-Sign Testing. If you have questions about E-Sign, contact Butch Dillon-Townes, x7563.

Facilities Management and Logistics

JLab Energy Reduction Annual Test Set for Thursday, June 14
JLab has been notified by Virginia Dominion Power to reduce its electric demand on Thursday, June 14, as part of the annual electric load reduction test. For planning purposes, don't start heavy electrical load work, power ups or tests after 1 p.m. on June 14. Additional information can be found in this All-Staff memo.

Environment, Safety, Health and Quality

Working Gloves
Many JLab workers use varying types of gloves to protect their hands or to protect equipment from damage from oils and materials on the skin. But not all protective gloves are equal. The key to picking the appropriate glove for the task is to first know what hazards are present. Are the hazards from cutting, carrying (anti-slipping), welding, cryogenic gasses, dirt or protection from a variety of chemicals? Further, would exigent circumstances for the hazard or task require more than the general-purpose glove for the hazard, such as a glove resistant to a higher range of temperatures, one that is impervious to chemicals under certain conditions, or one that extends past a certain length?

Your work documents should list specifically what type of glove should be used for the job. If it does not, then it is time to stop and ask your supervisor. If no one knows, then it is time to ask Industrial Hygiene (Jen Williams, x7882) for help. Most gloves are available in the Stock Room for the asking, but make sure you are asking for the correct one.

Computing and Networking Infrastructure

CNI Maintenance Period Set for June 19, 5-7 p.m.
The CNI group is planning a maintenance period on Tuesday, June 19, 5-7 p.m. During this time, Linux and Windows patches will be released to all JLab-managed computers. Additionally, updated packages from Firefox, Thunderbird, Adobe Flash and Adobe Shockwave will be delivered. Plan to reboot your computer as soon as possible on Wednesday in order to finalize the installation of these important security updates. If you have questions or concerns, or any time you experience any difficulties with your JLab computer, contact the IT Division Helpdesk, x7155.

Email Migrations into New System Continue
The CNI group is continuing to migrate staff and some users into the new email and calendar suite, Zimbra. These migrations are going well, with nearly 768 staff and users migrated into Zimbra and about 120 still left to migrate. These migrations are occurring overnight, and you will receive an email around noon on the day you are scheduled to be migrated. For more information, see the article in the March 16 OnTarget newsletter.

Announcements

New Montage on the Month of May
The latest Montage by Lab Director Hugh Montgomery is now available. In this latest posting, Mont talks about the accomplishments of the past month and positive feedback that the lab has received from many quarters.

Education Seeks Projects for Summer Honors Interns
JLab's Science Education team is seeking ideas and suggestions for projects, and project and mentor volunteers, for the lab's 2012 High School Summer Honors Program, June 25 to Aug. 3. Students chosen for the program have a strong academic record and a strong desire to learn about the lab's science and technology. Lab scientists, engineers and other technical managers who are interested in serving as a mentor to these high-achieving high school students and have a project, or number of projects, to be accomplished this summer, are asked to send a description of the work to be assigned to Brita Hampton, x7633, as soon as possible.

Tracking Thomas at JLab
Little Thomas is visiting all corners of the JLab campus. If you can identify his location this week, email Kandice Carter with your guess. Guesses are accepted through Friday.

Congratulations this week go to Samika Hawkins, who was the only person to correctly identify the June 6 location. Check out the Tracking Thomas webpage for a better view of his last location and this week's new mystery photo.

JLab Calendar of Events

June 14: Accelerator Colloquium and Public Lecture: ADS and the MYRRHA project
June 18: Safety Shoe vendor onsite
June 18-22: Program Advisory Committee Meeting (PAC39)
June 26: Colloquium and Public Lecture: Hurricanes!
July 4: Independence Day holiday, JLab closed
Jule 9-13: Geant4 Tutorial