November 13, 1990 - Blue Sheet

PDF Download

Project Progress Summary

13 November 1990

Injector and Front End Test

  • No report received: Progress covered under specific systems.

WBS 1

  • Two single-cell cavities have been electron-beam welded.
  • The old C’ pair (IP008/IP009) has been tested with excellent results. CE007/CE008 pair also tested fine. They were to be transferred to the cryounit assembly area 12 November.
  • IA014/IA015 had the dish valve assembly replaced and was to be tested 12 and 13 November.
  • The Production Chem Room is in commissioning, prior to final checkout to confirm safe operability.
  • Two cavity pairs for cryomodule #3 are in their helium vessels; other pairs being delivered will go into helium vessels this week.
  • Cryomodule #2 (in the test cave) is being warmed up to room temperature because the initial cooldown was too slow.
  • The batch of 12 windows has been RF tested and will be transferred to the cavity assembly area this week.
  • Routine testing of HOM loads revealed a potential problem with their power absorption capability at 2K. The problem is being verified and analyzed through further testing. Production assembly and testing continues on cryomodules #2 and #3, which contain HOM loads like the one that exhibited the potential problem, as their performance is acceptable for (and can be verified in) the Front End Test.

WBS 2

FET:

  • The vacuum pipe has been installed through the second cryomodule awaiting the 45-MeV spectrometer components to complete installation.
  • Bolt patterns for the 450MeV spectrometer and dumps were located.

Stands:

  • The contract for all the adjustment cartridges for stands was let at substantially below cost book estimates.

Vacuum:

  • The test centering of a captured beam pipe in a quadrupole was found acceptable for both centering and repeatability. A flange design is being tested this week that, if proven successful, will ensure perpendicularity to center a beam position monitor.

Alignment:

  • A simulation of an arc quadrupole alignment scheme was performed and analysis of results is in process.

WBS 3

RF Controls:

  • A full FET complement of most types of control boards is now on hand. We are starting to testy and calibrate them in preparation for installation in the control modules.
  • We are having problems with the INTEL “C” compiler (for the embedded microprocessor code). We have isolated the fault to about ten lines of code that use a floating-point array. The previous code used for the injector test did not use FP arrays. INTEL and our software people are working closely and intensely to bring this to a quick resolution.

RF Power:

  • We now have a total of 63 klystrons and 46 circulators on hand at CEBAF.
  • The sixteen couplers and transitions from Unique Systems are through customs and now at CEBAF. We started testing the units last Friday.
  • Work towards the full test of the capture section 10-kW HPA is almost complete. We will be ready for power testing as soon as we have an operating control module.

WBS 4

  • Successfully tested two Rev. C Trim System regulator boards under load for several days.
  • E-1 service building transformer and breaker panel installation is complete.
  • The trim rack assembly operation was moved from Blue Crab Road to the EEL building on Saturday, 10 November.

WBS 5

Safety:

  • FET and north linac ODH system fully operational.
  • Final checkout of FET Personnel Safety System has begun.
  • FET FSD (Fast shutdown) system is installed and operational.
  • All boundary radiation monitors delivered.

Diagnostics:

  • 50-ohm line driver chassis is complete.
  • Faraday cup is complete (vacuum leak discovered).
  • Chopper aperture stepper motor ready for test.
  • Debugging chopper software.
  • INTEL microprocessor experiencing floating point errors when accessing arrays; working problem with INTEL (see WBS 3 report).

WBS 6

  • No Report Received.

WBS 7

  • No Report Received.

WBS 8

Accelerator Enclosure:

  • Continued joint punch list inspections n facilities not yet accepted by CEBAF.

End Stations:

  • Continued repair work on beam tunnels A and C.
  • Completed the structural slab on grade in beam dump B.
  • Continued installing steel reinforcing and forms for the walls in Hall A.
  • Continued waterproofing the counting house and installed cableway pipes.
  • Received the 120-in. pipe for the tagged photon beam dump in Hall B.

EEL Building:

  • The subcontractor continued correcting punch list items.

Support Services

Machine Shop:

  • Move 70% complete. Completion expected early this week. No significant work interruption.
  • Completed waveguide elbows for WBS 1.
  • Completed hardware for HOM filter brackets (WBS 3).

Installation and Integration

  • Systems Integration Meeting was held today. Eleven song sheets were signed off by WBS 2, 4, 5, 9, and Alignment Group.

Tunnel ODH Status

  • Due to heat exchanger problems at the CHL, the tunnel and service buildings are not yet ODH classified areas. Staff will be alerted at least a week before ODH classification takes effect.

Material Services

  • Effective Monday, 12 November, the Material Services group ceased operations in the VARC building and commenced operations in the EEL building. Services provided in the EEL are: property control, shipping and receiving, mail distribution, central stores distribution.
  • Airborne Express pickup points for general correspondence will remain at CEBAF Center and the VARC building.
  • Questions can be directed to the material Services staff at the following extensions: Teresa Danforth, 7364; Joan Davis, 7580; Estelle Seeley, 7581.

Computer Center

  • A DEC Ultrix/RISC 5000, CEBAF9, is now up and running applications.
  • The requisition and receive log Ingres databases have been moved to CEBAF 4.
  • The local area network (LAN) has been extended to the EEL building.