Project Progress Summary
24 July 1990
Injector
-Cryounit A’ was cooled down after repair of the beamline vacuum accident. Both cavities reached 5 MV/m gradient, although at reduced Qo (~5 x 10^8), permitting full-energy injector tests to resume.
-Preparations for fully computer-controlled operation of the capture accelerator RF system are nearly complete, and everything appears satisfactory.
-
-
-
Project Progress Summary
28 August 1990
Announcements
Since Monday, 3 September is a holiday, please submit your status reports on
Tuesday, 4 September for issue on Wednesday, 5 September. Have a SAFE
weekend!
The radiation worker training scheduled for Wednesday, August 29, 1990 has been
postponed. A new schedule will be issued shortly.