  • PDF Download

    Project Progress Summary

    15 January 1991

    Multidisciplinary Appraisal

  • PDF Download

    Project Progress Summary

    8 January 1991

    Injector and Front End Test

    • No report received

    WBS 1

  • PDF Download

    Project Progress Summary

     

    23 January 1991

    Multidisciplinary Appraisal

    • DOE Oak Ridge Operations has begun its ES&H and QA appraisal of CEBAF. One group leader will be present the entire two weeks; reviewers for specific areas will b present for either the first or second week. Specific areas to be covered are as follows, with the number of reviewers in parentheses after each topic.

    This Week

  • PDF Download

    Project Progress Summary

    January 29, 1991

    Multidisciplinary Appraisal

    DOE Oak Ridge Operations will complete its EH&S and QA appraisal of CEBAF this week. Specific areas being covered this week are as follows, with the number of reviewers in parentheses after each topic:

    Environment (3)

    Health Physics (1)

    Quality Assurance (2)

     

  • PDF Download

    Project Progress Summary

    February 20, 1991

    \Message from the Director

    CEBAF is recognized as a very successful project and laboratory, due to the caliber, commitment, and enthusiasm of the staff. You make our achievements and progress possible! Let’s continue to get our job done safely and right (QA), and continue to pay attention to housekeeping in all work areas. You are the most impressive team I have had the pleasure to lead. Thanks!

  • PDF Download

    Project Progress Summary

    February 20, 1991

    WBS 7

    • This weekend we operated at 4 K to the tunnel, incorporating a two-turbine liquid nitrogen cycle.
    • On Tuesday, 19 February, we started the warm vacuum pump and went to 2 K in the tunnel. By 4 p.m., both the cryomodule and the quarter-cryomodule were at 2 K.

    WBS 1

  • .primery-menu-style ul li.last.leaf { margin-top: 50px !important; } * {box-sizing:border-box} body {font-family: Verdana,sans-serif;} .mySlides {display:none} /* Slideshow container */ .slideshow-container { max-width: 1000px; position: relative; margin: auto; } /* On hover, add a black background color with a little bit see-through */ .prev:hover, .next:hover { background-color: rgba(0,0,0,0.8); } /* Caption text */ .text { color: #f2f2f2; font-size:
  • PDF Download

    Project Progress Summary

    March 5, 1991

    WBS 1