Project Progress Summary
23 October 1990
Semi-Annual Review
Project preparations for a November review are continuing, although the date has not been set yet.
Injector and Front-End Test
-Beam viewers in the injector became operational in preparation for a 100-kV beamline test planned for this week.
-
-
Jefferson Lab Weekly Briefs
April 10, 2013Physics
Registration Open for Annual Users Group Meeting
The 2013 JLab User's Group Annual Meeting will take place on May 29-31. The program includes a variety of physics talks, presentations from the Users Group Board, laboratory management and funding agencies, and talks from the new APS fellows and prize winners. Register now online. -
Project Progress Summary
10 July 1990
Injector & Front-End Test
-Injector tests during the past week have been fairly successful. We have delivered good beam to WBS 3 for their evaluation of the RF control system, and to WBS 5 for tests of the beam position monitors. Improvements to the control software have brought us to the point where setting up a good 5-MeV beam is (almost) routine. (C. Sinclair)
-
-
-
Project Progress Summary
13 November 1990
Injector and Front End Test
- No report received: Progress covered under specific systems.
WBS 1
-
-
Project Progress Summary
20 November 1990
No Project Progress Summary will be published on 4 December (during the week of the Semi-Annual Review).
Injector and Front End Test