Project Progress Summary
20 November 1990
No Project Progress Summary will be published on 4 December (during the week of the Semi-Annual Review).
Injector and Front End Test
-
Accelerate Industrial Processes Workshop
-
-
-
Project Progress Summary
8 January 1991
Injector and Front End Test
- No report received
WBS 1
-
Project Progress Summary
23 January 1991
Multidisciplinary Appraisal
- DOE Oak Ridge Operations has begun its ES&H and QA appraisal of CEBAF. One group leader will be present the entire two weeks; reviewers for specific areas will b present for either the first or second week. Specific areas to be covered are as follows, with the number of reviewers in parentheses after each topic.
This Week
-
Project Progress Summary
January 29, 1991
Multidisciplinary Appraisal
DOE Oak Ridge Operations will complete its EH&S and QA appraisal of CEBAF this week. Specific areas being covered this week are as follows, with the number of reviewers in parentheses after each topic:
Environment (3)
Health Physics (1)
Quality Assurance (2)
-
Project Progress Summary
February 20, 1991
\Message from the Director
CEBAF is recognized as a very successful project and laboratory, due to the caliber, commitment, and enthusiasm of the staff. You make our achievements and progress possible! Let’s continue to get our job done safely and right (QA), and continue to pay attention to housekeeping in all work areas. You are the most impressive team I have had the pleasure to lead. Thanks!
-
Project Progress Summary
February 20, 1991
WBS 7
- This weekend we operated at 4 K to the tunnel, incorporating a two-turbine liquid nitrogen cycle.
- On Tuesday, 19 February, we started the warm vacuum pump and went to 2 K in the tunnel. By 4 p.m., both the cryomodule and the quarter-cryomodule were at 2 K.
WBS 1