JEFFERSON LAB SEARCH

(Show results from this date)
(Show results to this date)
*Use spaces between key words, no punctuation needed *Sign In for authenticated content

  • About JAG

    The Jefferson Lab Activity Group (JAG) was formed to enhance employee morale through various recreational, social, and athletic activities.  Part of JAG's overall function is to promote and implement new ideas in support of DOE and DC policies.  JAG also monitors new and existing recreational programs to ensure benefit to the greatest cross section of the lab community. 

  • Committee Working Documents and some useful information

    Everything you need for the FY23 review meeting:

    The Indico website for October 30-31, containing the agenda and public Zoom address, is https://indico.jlab.org/event/751/ .

  • PDF Download

    Project Progress Summary

    5 September 1990

    Injector and Front-End Test

    -Waveguide connections to the first HPA have been done and klystrons are being installed.

    -Plumbing for injector service building has been installed. LCW system operational.

    -The approach has been defined for cryomodule installation sequence. First cryomodule slated to be installed by 7 September.

  • PDF Download

    Project Progress Summary

    11 September 1990

    Injector and Front-End Test

    -First cryomodule is in the tunnel.

    -Four klystrons have been installed in the first HPA.

    -Copper cavities (chopper 1 & 2, capture section) have been installed on the injector girder as injector reassembly continues.

    -Electronics have been reinstalled in high-voltage cage for the gun. First try to run gun from control room this week.

  • PDF Download

    Project Progress Summary

    18 September 1990

    Injector and Front-End Test

    -Injector main pump and vacuum manifold installed.

    -Fabrication of 5-MeV chicane vacuum chambers started on schedule at University of Illinois.

    -Cables for injector magnets and controls pulled.

    -First cryomodule has been mounted on its stands and cabling is proceeding.

  • PDF Download

    Project Progress Summary

    16 October 1990

    Injector and Front-End Test

  • PDF Download

    Project Progress Summary

    23 October 1990

    Semi-Annual Review

    Project preparations for a November review are continuing, although the date has not been set yet.

    Injector and Front-End Test

    -Beam viewers in the injector became operational in preparation for a 100-kV beamline test planned for this week.