Help Get More Beam Time
- Provide someone to act as a guard when your hall is being locked up.
- Provide a qualified ARM (Assigned Radiation Monitor) for radiation surveys.
- Allow the operators at least 5 minutes before calling after the beam trips off. they are busy trying to identify and correct the problem.
- Inform the Program Deputy in advance of all scheduled activities for the upcoming shifts. This allows the operators to prepare, and not waste valuable beam time.
- Notify the control room of any configuration changes that may alter the beam orbit (i.e. changing the state of magnets, radiators, rasters, target cells)
- Try not to schedule activities during the operator "passdown" periods. These periods occur for about 15 minutes at 0000, 0800, and 1600.
- Try not to schedule activities during System Checks. System Checks usually occur at 1630 every evening.
Things You Should Know
-
It takes about 15 minutes to restore beam to the hall after a Controlled Access.
-
ABU (Available Beam in Use): The number of hours you use the beam for any part of your scheduled program during the shift. This includes energy measurements, Moeller runs, current calibrations, etc.
-
Swing Shift: 1500-2300
-
Day Shift: 0700-1500
-
Owl Shift: 2300-0700
-
-
Hall B: The nA BPM position data is unreliable below 1nA.