  • Jefferson Lab Weekly Briefs
    December 10, 2015

    12 GeV Upgrade
    Late last month, the new spectrometer in Hall C was rotated to its maximum angle relative to the electron beam for the first time. This is a triumph for those who designed, surveyed and installed the Super High Momentum Spectrometer, since it must come very close to the curved wall of Hall C. After Jefferson Lab staff removed or relocated a final few items from the wall, the SHMS was rotated to a scattering angle of 40.2 degrees. The design specification calls for reaching at least 40 degrees.

  • Jefferson Lab Weekly Briefs
    November 25, 2015

    Physics
    Jefferson Lab Published Journal Articles, Nov. 16-20

    • H. S. Jo et al. (CLAS Collaboration). "Cross sections for the exclusive photon electroproduction on the proton and Generalized Parton Distributions." Phys. Rev. Lett. 115, 212003.

    Remember to submit your papers for approval to the Jefferson Lab Publications database.

  • Jefferson Lab Weekly Briefs
    November 18, 2015

    12 GeV Upgrade
    12 GeV Project installation work in Hall B is increasing in many areas. In addition to welding on the Torus magnet, electrical and electronic work on the power supplies and racks has ramped up. Hall C continues testing and measurements of the Horizontal Bend magnet and power supply, along with preparations for the arrival of additional superconducting magnets in 2016.

    Physics
    Jefferson Lab Published Journal Articles, Nov. 2-6

  • Jefferson Lab Weekly Briefs
    October 15, 2014

    Physics
    Remember to submit your papers for approval to the Jefferson Lab Publications database.

  • Jefferson Lab Weekly Briefs
    October 8, 2014

  • Jefferson Lab Weekly Briefs
    September 24, 2014

    12 GeV Upgrade
    The voltage-tracking regulators for the extraction YA’s are operational, and control screens have been implemented. This completes the scope for the 12 GeV Project power systems. The scope for the 12 GeV Project safety systems has also been completed. The magnets for the fast-feedback system for the Hall D beamline have been installed, and the first of the nano-Amp beam position monitors for the Hall D beamline has been installed.

  • Jefferson Lab Weekly Briefs
    September 10, 2014

    Physics
    Jefferson Lab Published Journal Articles, September 1-7

  • Jefferson Lab Weekly Briefs
    August 20, 2014

  • Jefferson Lab Weekly Briefs
    August 13, 2014

    12 GeV Upgrade
    Work on the voltage-tracking regulators for the extraction YA’s remains on hold, awaiting restoration of power to the service building. The current transducer for the Hall D leg of the beam envelope limit system has been received. The magnets for the fast-feedback system for the Hall D beamline have been completed. The cavities for the nanoAmp beam position monitor system for the Hall D beamline are being welded and will then be sent out for plating.

  • Jefferson Lab Weekly Briefs
    August 6, 2014