Project Progress Summary
18 September 1990
Injector and Front-End Test
-Injector main pump and vacuum manifold installed.
-Fabrication of 5-MeV chicane vacuum chambers started on schedule at University of Illinois.
-Cables for injector magnets and controls pulled.
-First cryomodule has been mounted on its stands and cabling is proceeding.
-
-
Project Progress Summary
23 October 1990
Semi-Annual Review
Project preparations for a November review are continuing, although the date has not been set yet.
Injector and Front-End Test
-Beam viewers in the injector became operational in preparation for a 100-kV beamline test planned for this week.
-